Construction updates:
The Northfield High School Reimagine project has begun in earnest, and regular construction updates will be provided in district and building newsletters and on this webpage.
During construction, the preferred route for parking and building access will be via Raider Drive and Door 10. We encourage all visitors to use this entrance throughout the summer.
Please note that due to continued progress on site, there will be increased construction traffic along Raider Drive. Only construction vehicles are to enter the construction zone through the gated fence.
Those attending football, volleyball, or soccer games should use Raider Drive on the southwest corner of the map below to drop off or park for entry to Memorial Field or to enter Door 10 at the high school. Those attending tennis matches should enter the site using Division Street on the east side of the map to drop off or park.
We appreciate your patience and cooperation as we reimagine Northfield High School.
Construction Cameras
Cameras have been installed to view construction progress. Camera 1 is located above the Memorial Field concession stand and will provide images of the south parking lot construction, music addition construction, and expanded gymnasium construction. Camera 2 is located above the main entrance door 1 on the roof and will provide images of the classroom addition. Click the link below to view both camera views.
📷 View the Reimagine Northfield High School Construction Camera Timelapse
A drone was also flown over the site on August 6, 2026 and shows aerial views of the underground utility work being completed.
🎬 View the August 6, 2026 Drone Flight over the Reimagine Northfield High School Construction Site
Construction activity that took place the week of August 24-28, 2026:
-
The northeast parking lot was paved with asphalt.
- The underground storm structure backfill and pavement sub-base preparation is ongoing.
- Sanitary and storm sewer concrete structures and piping are being set in place as they are delivered to the site.
- Underground conduits for parking lot lighting and fiber conduits were completed.
- The Raider Drive storm sewer connection and new water main connection to the existing main was completed.
- Geothermal and lateral piping and conduits were placed underground and backfilled.
- The concrete walkway was poured from Door 1 (main entrance) to the northeast parking lot.
- The site fence was relocated outside of Door 1 (main entrance) and the new concrete walkway.
- Demolition activities in PE 01 and the auxiliary gym continue.
Anticipated activity for the week of August 31- September 4, 2026:
-
Continue to place utility structures and piping underground as they are delivered to the site.
- Continue demolition activities, such as mechanical and electrical removals inside the existing building at Area N (the auxiliary gym and PE 01).
- Layout and install curb and gutter.
- Pave south parking lot with asphalt.
- Pave drive lane with asphalt.
- Stripe parking lot and drive lane.
– Updated August 31, 2026
Recent Presentations to the Board:
You can follow the project’s progress by reviewing the construction updates provided at each board meeting:
📝 June 24, 2026 Bid Award
📺 Video of the June 24, 2026 Presentation to the Board
📽️ Video tour (09.22.2025) (Suggested: Increase playback speed to 1.5x for a swifter walkthrough)

