Construction updates:
The Northfield High School Reimagine project has begun in earnest, and regular construction updates will be provided in district and building newsletters and on this webpage.
The map below shows overall parking on the Northfield High School campus, and highlights the parent pick up and drop off route, as well as designated parking for students and staff. It also highlights handicap accessible and visitor parking locations.
The map below highlights the new student parking lot and traffic flow for parent drop off and pick up.
Students parking in the new Memorial Field parking lot will need to enter/exit through Door 10 before, during, and after school.
Please note that due to continued progress on site, there will be increased construction traffic along Raider Drive. Only construction vehicles are to enter the construction zone through the gated fence.
Construction activity that took place the week of October 26-30, 2026:
- Backfilled newly-poured concrete foundation walls in Area R (classroom addition).
- Poured concrete footings in Area R (classroom addition).
- Poured concrete footings and walls in Area G (storm shelter).
- Continued excavation and added crushed rock for footings in Area G (storm shelter).
- Continued electrical conduit rough-ins in Area N (electrical room).
- Removed metal panel and parapet in Area N (electrical room) in preparation for new parapet and roof structure.
Anticipated activity for the week of November 2-6, 2026:
- Continue concrete footing and foundation installation at Areas P, Q, and R (classroom addition).
- Continue underground electrical work in Area N (electrical room).
- Remove precast roof planks in Area N (electrical room).
- Excavate Area G (music addition) and begin work on concrete footings.
- Demolition of Door 1 canopy.
- Backfill Area N (auxiliary gym) former mezzanine space.
- Install concrete footings/foundation in Area G (music addition).
We appreciate your patience and cooperation as we reimagine Northfield High School.
– Updated November 2, 2026
Construction Cameras
Cameras have been installed to view construction progress. Camera 1 is located above the Memorial Field concession stand and will provide images of the south parking lot construction, music addition construction, and expanded gymnasium construction. Camera 2 is located above the main entrance door 1 on the roof and will provide images of the classroom addition. Click the link below to view both camera views.
📷 View the Reimagine Northfield High School Construction Camera Timelapse
Drone Footage
A drone was also flown over the site on and shows aerial views of the progress being made on the site:
🎬 View the Sept.18-25 time lapse of the classroom addition.
This shows progress from the past week of rain to excavation of concrete footing trenches, to rebar, to first concrete footing pours.
🎬 View the Sept. 24 Drone Flyover No. 1.
This shows the new music/storm shelter addition, new south parking lot, geothermal well field, and classroom addition. Excavations and soil correction will continue for the next two and a half weeks. Concrete footings and foundation work is scheduled to start Oct. 14 on the music/storm shelter addition.
🎬 View the Sept. 24 Drone Flyover No. 2.
This shows the new classroom addition moving east and then south towards the geothermal well field. Concrete footings and foundation work will continue through the next month and a half. The first precast wall is scheduled to arrive and be set on Nov. 11.


