Construction updates:
The Northfield High School Reimagine project has begun in earnest, and regular construction updates will be provided in district and building newsletters and on this webpage.
The map below shows overall parking on the Northfield High School campus, and highlights the parent pick up and drop off route, as well as designated parking for students and staff. It also highlights handicap accessible and visitor parking locations.
The map below highlights the new student parking lot and traffic flow for parent drop off and pick up.
Students parking in the new Memorial Field parking lot will need to enter/exit through Door 10 before, during, and after school.
Please note that due to continued progress on site, there will be increased construction traffic along Raider Drive. Only construction vehicles are to enter the construction zone through the gated fence.
Construction activity that took place the week of November 16-20, 2026:
- Wrapped up concrete footings/foundation installation in Areas P, Q, and R (classroom addition).
- Continued underground electrical work in Area N (electrical/mechanical room) and exterior.
- Excavated Area G (music addition) and began work on concrete footings.
- Poured concrete footing in Area N (electrical/mechanical room)
- Backfilled Area N (auxiliary gym) former mezzanine space.
- Installed concrete footings/foundation in Area G (storm shelter).
- Installed concrete footings/foundation in Area H and J (activity center).
- Surveyed and laid out precast walls in Area P (classroom addition).
- Completed remaining asphalt paving and patching.
Anticipated activity for the week of November 23-27, 2026:
- Waterproof and backfill remaining areas in Areas P, Q, and R (classroom addition).
- Demolish Door 10 canopy.
- Continue underground electrical work in Area N (electrical/mechanical room) and exterior.
- Continue excavation of Area G (music addition) and work on concrete footings.
- Install concrete footings/foundation in Area G (storm shelter).
- Install concrete footings/foundation in Area H and J (activity center).
- Begin masonry wall installation in Area P (classroom addition).
- Infill concrete floor in Area N (electrical/mechanical room).
We appreciate your patience and cooperation as we reimagine Northfield High School.
– Updated November 23, 2026
November 23 Board Presentation
At the November 23, 2026 school board meeting, Knutson Construction and Wold Architects and Engineers presented an update on the Reimagine Northfield High School project.
📝 View the presentation slide deck
📺 Watch the November 23, 2026 presentation to the board
Construction Cameras
Cameras have been installed to view construction progress. Camera 1 is located above the Memorial Field concession stand and will provide images of the south parking lot construction, music addition construction, and expanded gymnasium construction. Camera 2 is located above the main entrance door 1 on the roof and will provide images of the classroom addition. Click the link below to view both camera views.
📷 View the Reimagine Northfield High School Construction Camera Timelapse
Drone Footage
A drone was also flown over the site and shows aerial views of the progress being made on the site:
🎬 View the November 12 Drone Flyover
This video provides an aerial view of the Reimagine Northfield High School project as of November 12, 2026. The footage shows the footprint of the classroom addition, the location of the geothermal well field, and early progress on the activity center/expanded gymnasium.


