Construction updates:
The Northfield High School Reimagine project has begun in earnest, and regular construction updates will be provided in district and building newsletters and on this webpage.
Construction Cameras
Cameras have been installed to view construction progress. Camera 1 is located above the Memorial Field concession stand and will provide images of the south parking lot construction, music addition construction, and expanded gymnasium construction. Camera 2 is located above the main entrance door 1 on the roof and will provide images of the classroom addition. Click the link below to view both camera views.
📷 View the Reimagine Northfield High School Construction Camera Timelapse
A drone was also flown over the site on August 6, 2026 and shows aerial views of the underground utility work being completed.
🎬 View the August 6, 2026 Drone Flight over the Reimagine Northfield High School Construction Site
Construction activity that took place the week of August 10-14, 2026:
-
Water main utilities excavation and piping installation continued.
-
Underground storm structure backfill and pavement sub-base preparation is ongoing.
-
Sanitary and storm sewer concrete structures and piping were delivered to the site and set in place.
- Geothermal lateral piping work with mobilizations and excavations are starting in the existing building and working its way out to the geothermal field.
Anticipated activity for the week of August 17-21, 2026:
-
Continue water main excavation and piping installation at the NE parking lot.
- Prepare old tennis, basketball courts for temporary asphalt paving and striping.
- Continue to place utility structures and piping underground as they are delivered ot the site.
- Continue backfilling activities over underground storm structure to prepare parking lot subgrade.
- Continue geothermal lateral piping work.
- Start to remove the large tree outside Door 1 (main entrance).
- Start additional demolition activities, such as mechanical and electrical removals inside the existing building at Area N (auxiliary gym and PE01).
- Prep and pour new sidewalks that will serve as walkways into main and activity entrances.
During construction, the preferred route for parking and building access will be via Raider Drive and Door 10. We encourage all visitors to use this entrance throughout the summer.
Please note that due to continued progress on site, there will be increased construction traffic along Raider Drive. Only construction vehicles are to enter the construction zone through the gated fence.
Those attending football, volleyball, or soccer games should use Raider Drive on the southwest corner of the map below to drop off or park for entry to Memorial Field or to enter Door 10 at the high school. Those attending tennis matches should enter the site using Division Street on the east side of the map to drop off or park.
– Updated August 17, 2026
Recent Presentations to the Board:
You can follow the project’s progress by reviewing the construction updates provided at each board meeting:
📝 June 24, 2026 Bid Award
📺 Video of the June 24, 2026 Presentation to the Board
📽️ Video tour (09.22.2025) (Suggested: Increase playback speed to 1.5x for a swifter walkthrough)

