Planning for the Future of Our Managed Buildings
The Northfield School District Board of Education approved the Master Facilities Plan Executive Summary at its meeting on November 28, 2016.
Por favor, elija traducir el sitio al español o visite esta página para obtener más recursos en español.
Planning for the Future of Our Managed Buildings
The Northfield School District Board of Education approved the Master Facilities Plan Executive Summary at its meeting on November 28, 2016.
The District embarked on a long-term master facilities planning process in June 2014 and culminates with this Master Facilities Plan proposal. The Master Facilities Plan includes two components: a building life cycle plan and a deferred maintenance plan. The building life cycle plan considers the physical, environmental, and educational adequacy of our current buildings. The Master Facilities Plan Executive Summary will be updated on an annual basis and reviewed with the Board of Education. In addition, the estimated costs will be updated on an annual basis.
The Master Facilities Plan was developed between June 2014 and October 2016. Below is a timeline reviewing the process.
Physical, Environmental and Educational Adequacy
District consultant ATS&R identified four potential building life cycle management pathways as a result of the planning process. Based on stakeholder feedback, this Executive Summary identifies two building life cycle management projects as the prioritized projects for the District. These projects include:
The Board could also consider Pathway 4, which includes both options included above.
The District will update the estimated cost for each prioritized project on an annual basis and present it to the Board as part of the annual capital projects budget presentation.
Year | Elementary Project | High School Project | Totals |
2016 | $28.4 million | $76.5 million | $104.9 million |
2017 | $30.5 million | $78.5 million | $109 million |
2018 | $33.95 million-$36.89 million | $85.5 million | $119.45 million – $122.39 million |
The District’s deferred maintenance/10-year plan is the second portion of the Master Facilities Plan. This document replaces the deferred maintenance plan shared by ATS&R in February 2015. Since this time, the Minnesota legislature has enacted the Long Term Facilities Maintenance Revenue Program that requires School Boards to annually approve a 10-year plan. In an effort to be efficient, this is proposed to be the second part of the Master Facilities Plan and would be approved on an annual basis when the capital projects budget is approved.
The Board would authorize projects associated with the Long Term Facilities Maintenance 10-year plan on an annual basis in conjunction with the annual capital budget presentation. At that time, the Board would also review the Building Life Cycle Management plan and determine if conditions necessitate activating a bond campaign for one or both of the identified “next projects.”
Many Master Facilities Plans have formal benchmarks that signal activating a particular project. These benchmarks are often associated with enrollment, significant deterioration of the facility’s exterior envelope, or significant deferred maintenance needs. The District will initiate a Facilities Advisory Committee comprised of Board members, parents/community members, and staff to review these benchmarks on an annual basis and provide a report to the Board on the current state of the District’s facilities each year in March along with recommendations for considering portions of the plan for the following school year.
Please contact Superintendent Matt Hillmann or Director of Buildings and Grounds Cole Nelson with questions about the Master Facilities Plan.